From five-month lead times to three-day call-off

A leading European manufacturer of infrastructure products.

  • Infrastructure and utilities
  • Supplier management
  • Quality and compliance
  • Logistics and customs
  • Local stockholding
3 daysLead time, down from around five months
20%Saving against the previous supply route
10,000sUnits supplied every year

The challenge

The customer was already buying high volumes of fabricated steel frames directly from Asia. Factory prices were competitive, but production scheduling, shipping, customs clearance and quality were hard to control, and frames had to consistently meet the BS EN ISO 1461 hot-dip galvanising standard.

Buying direct meant an effective lead time of around five months. With high volumes and supply continuity critical, changing the supply model carried real risk.

What MMS did

  • Took ownership of supplier management and production scheduling
  • Carried out factory audits and pre-shipment inspections
  • Checked galvanising and quality against BS EN ISO 1461 before shipment
  • Managed freight and customs clearance end to end
  • Held finished stock in Northern Ireland so the customer could call off as needed

The result

The practical lead time fell from around five months to three days, with an estimated 20% saving compared with the previous route.

The customer also gained better control of galvanising compliance, more predictable supply and far less logistics, customs and supply chain admin.

How the relationship grew

What began as a single fabricated steel requirement is now a broader supply programme, with MMS managing significant volumes and inventory on the customer’s behalf.

Buying direct from overseas and losing control of lead times and quality? Talk to us.

More case studies

Heating, ventilation and air conditioning

Taking the risk out of material choices on a new product launch

A UK heating systems manufacturer launched a new range with confidence after MMS guided material selection and finish across multiple plastic components.

  • New product introduction
  • Material selection
  • Quality and compliance

Quarrying, crushing and screening

One partner for 25 bespoke parts on a new flagship machine

An aggregates equipment manufacturer saved 20% and gained three-day local supply after MMS managed 25 bespoke parts for a new flagship machine.

  • Supplier qualification
  • Quality and compliance
  • Logistics and customs
  • Local stockholding

Medical equipment

Securing supply through a period of rapid growth

A healthcare equipment manufacturer kept production running through rapid growth with a flexible four-month stock buffer held by MMS.

  • Supply continuity
  • Local stockholding